When is the best time to schedule an FAT?
Times can vary depending on the complexity of the system and the corresponding FAT, but they are typically scheduled 2-4 weeks prior to the ship date to help maintain on-time delivery. The duration of the FAT can be anywhere from one day up to a couple of weeks.